IAS 23 suspension of capitalisation: construction delays

Decide which months belong in asset cost, document interrupted work, and reconcile the interest entries.

When does IAS 23 suspension of capitalisation matter?

IAS 23 suspension of capitalisation becomes a practical question when a construction project slows down but the bank keeps charging interest. Before posting another month to construction in progress, establish what work continued, what stopped, and for how long. A project described as “on hold” may still involve substantial engineering work; a project described as “ongoing” may have no active development at all.

The [IFRS Foundation’s IAS 23 overview](https://www.ifrs.org/issued-standards/list-of-standards/ias-23-borrowing-costs/) explains the underlying distinction: borrowing costs directly attributable to a qualifying asset form part of its cost, while other borrowing costs are expenses. Our [borrowing costs guide](/learn/borrowing-costs-ias-23) covers the wider recognition and measurement framework. Here, the focus is the interruption within an otherwise qualifying construction project.

Build the timeline before calculating the interest. Label the dates when development was active, when it was suspended, when it resumed, and when the asset became ready. Then connect those dates to the finance schedule. The payment date alone cannot tell you which period bears the expense.

The Saudi companies in the two examples are fictional. All amounts are in SAR, and the loans are simplified teaching arrangements with no fees, compounding, temporary investment income or changes in principal. Construction expenditure has been incurred from the start, all other capitalisation conditions are satisfied during eligible periods, and tax and impairment calculations are outside the examples. Monthly allocation uses equal twelfths of the annual interest by assumption. These assumptions keep attention on the timing decision.

How do you decide on IAS 23 suspension of capitalisation?

IAS 23 paragraphs 20–21 address extended interruptions in active development. They also distinguish periods of substantial technical and administrative work, and temporary delays necessary to prepare the asset. The [XRB’s equivalent IAS 23 text](https://standards.xrb.govt.nz/standards-navigator/nz-ias-23/) reproduces these common requirements; New Zealand-specific concessions are outside this article.

Use three questions in your working paper. First, which preparation activities actually stopped? Second, what meaningful development work continued elsewhere? Third, is the delay a necessary part of the preparation process? Answering only the first question can produce the wrong result when engineers are redesigning an essential system away from the site.

The standard does not supply a universal number of days that makes an interruption extended. Consider duration and circumstances together. A three-month inactive period in the first example is an assumed extended suspension on its stated facts, not a rule that automatically applies to every three-month delay. Record the reasons supporting your assessment so another accountant can understand the conclusion.

Routine site security, paying bills and preserving equipment do not by themselves demonstrate substantial development work. Ask for evidence of what changed: approved designs, completed technical assessments or necessary preparation deliverables. Equally, a quiet construction site is only one observation. Work that materially prepares the asset can happen in an engineering office.

For your own decision sheet, use columns for dates, activity, evidence, conclusion and reviewer. Put the conclusion after the evidence. This order helps prevent the accounting team from choosing a desired capitalised amount and searching for a description that supports it.

Example 1: an inactive warehouse project in Riyadh

Rimal Storage is building a warehouse in Riyadh. On 1 January it draws a specific SAR 3,000,000 loan at 8% annual interest and starts qualifying construction activity. A funding dispute stops all active development from 1 April through 30 June. No substantial technical or administrative preparation continues, and this interruption is not a necessary construction stage. Work resumes on 1 July and remains active through 31 December; the warehouse is still unfinished.

Annual borrowing cost is SAR 3,000,000 × 8% = SAR 240,000. Each month therefore contributes SAR 20,000. There are nine eligible months and three suspended months. Prepare the allocation before the [journal entry](/glossary#journal-entry):

Assume interest is paid in cash monthly. The annual summary is debit construction in progress SAR 180,000, debit finance expense SAR 60,000, and credit cash SAR 240,000. This summary combines the monthly entries; it is not an additional entry to post after those entries already exist.

For a single suspended month, debit finance expense SAR 20,000 and credit cash SAR 20,000. For a single eligible month, debit construction in progress SAR 20,000 and credit cash SAR 20,000. If interest were unpaid instead, the credit would be to interest payable under that different assumption.

The check is SAR 180,000 + SAR 60,000 = SAR 240,000. Resuming work in July does not move the April–June expense into the asset retrospectively. Keep those three months visible in the schedule so the year-end total can be traced to the interruption decision.

Example 2: engineering continues while the site pauses

Nakhil Manufacturing is constructing a production facility in Dammam. A specific SAR 2,400,000 loan carries annual interest of 6%, giving SAR 144,000 a year and SAR 12,000 a month. The project qualifies from 1 January. Physical construction pauses in March and April while engineers carry out substantial redesign work needed to integrate the facility’s safety and ventilation systems. Dated drawings, calculations and approvals support that work throughout both months.

On these facts, the physical pause does not suspend capitalisation: substantial preparation continues. Construction resumes in May. Substantially all activities necessary for intended use are complete on 30 September. The loan remains outstanding until year-end, but October–December borrowing costs are outside the capitalisation period.

With monthly cash interest payments, the combined entries debit construction in progress SAR 108,000, debit finance expense SAR 36,000, and credit cash SAR 144,000. Again, this is a summary, not a second posting. Transfer the completed facility’s full accumulated cost to the appropriate asset account separately; SAR 108,000 represents only the borrowing-cost component.

The example distinguishes a temporary interruption from final cessation. September is the last eligible month because of readiness, not because the lender stopped charging. The [PPE cost guide](/learn/ppe-capitalization-ias-16) helps connect the completed construction balance to the wider asset record. If you change the engineering facts to mere routine supervision with no substantial preparation, reassess March and April rather than copying the original answer.

What evidence belongs in the monthly close file?

A useful close file lets a reviewer reconstruct the decision without interviewing the project team again. Keep the loan schedule, project timeline and accounting allocation together. Attach the documents that explain each change of status, rather than a large folder with no indication of which document supports which month.

For Rimal, the file would include the dated instruction stopping development, confirmation that substantial preparation did not continue, and evidence of the July restart. For Nakhil, it would include engineering deliverables spanning March and April and the readiness assessment at September-end. A single email saying “work continues” offers much less explanation than a description of what was actually completed.

Reconcile interest paid or accrued to the two accounting destinations. A [general ledger](/glossary#general-ledger) reconciliation should show that capitalised interest plus expensed interest equals the borrowing cost being allocated. Then reconcile the capitalised part to construction in progress. This second comparison catches a spreadsheet that calculates the right number but never reaches the asset account.

Separate evidence dates from document creation dates. A report prepared in July may describe work performed in June. Ask which period the work relates to and whether the conclusion is supported. Do not assume that late paperwork automatically changes the underlying activity date.

As a practical workflow, assign a project contact to explain activity, a finance preparer to calculate the allocation, and a reviewer to challenge the conclusion. This is a suggested control arrangement, not a prescribed IAS 23 staffing requirement. The goal is a short, traceable explanation of the amount posted each month.

Which common mistakes change the result?

The most frequent error is treating the loan as the capitalisation timetable. A bank statement establishes a borrowing cost, but it does not establish that development remained active. In Rimal’s case, capitalising all SAR 240,000 would overstate the borrowing-cost component of the asset by SAR 60,000 and understate finance expense by the same amount before tax and any subsequent effects.

The opposite error is suspending whenever workers leave the site. Nakhil’s engineering evidence supports SAR 24,000 of capitalisation during March and April. Expensing that amount solely because construction paused would understate asset cost and overstate finance expense on the stated facts. The description of the work matters more than the label attached to the delay.

Other mistakes are easy to catch with a careful review:

  • Using an internal fixed-day threshold as though it were written in IAS 23.
  • Treating routine administration as substantial preparation without explaining the activity.
  • Adding previously expensed suspension-period interest to the asset after work resumes.
  • Continuing capitalisation after readiness because repayment has not occurred.
  • Posting an annual summary on top of monthly entries and counting the interest twice.

Check both the asset record and the [income statement](/glossary#income-statement). A balanced entry can still put the amount in the wrong account. If you identify an error in an already issued reporting period, evaluate the applicable error-correction requirements separately; the current examples do not prescribe a prior-period correction method.

Finally, an interruption may prompt other accounting questions about the project. Assess those under the relevant standards rather than assuming the suspension calculation resolves every consequence of the delay.

How do you explain the decision in a short accounting memo?

Write the memo so a colleague can follow the event, judgment and amount in that order. For Rimal, the event is the complete halt in development from April through June. The judgment is that the extended inactive period requires suspension on the stated evidence. The amount is three months at SAR 20,000, giving SAR 60,000 of finance expense.

For Nakhil, describe the engineering work before discussing the quiet site. Then explain why the March–April costs remain eligible and why September readiness ends capitalisation. This separates two judgments that can otherwise disappear inside a single nine-month multiplier. State the loan assumptions beside the calculation so the reviewer does not mistake a teaching simplification for the terms of an actual financing agreement.

A concise memo can use these prompts:

  • What changed in the project, and on which dates?
  • What preparation continued during the interruption?
  • Which documents support the period-by-period treatment?
  • What amount belongs in the asset and what amount is expensed?
  • Where do those amounts appear in the accounting records?

For final cessation and disclosure, consult IAS 23 paragraphs 22–26 in the cited standard text. The disclosures include the amount capitalised and the capitalisation rate used. A supporting memo makes those figures traceable, but it does not replace the required financial statement disclosures.

Finish with the unresolved facts, if any. A missing engineering report is a question to resolve, not evidence that either treatment is automatically correct. In a classroom exercise, state the assumption needed; in a company close, obtain the evidence and have the accounting conclusion reviewed.

How can you practise the interruption decision?

Start with the Rimal timeline and cover the answer table. Allocate the twelve monthly interest amounts yourself, write the entries, and reconcile the total. Then explain the April–June treatment aloud in one sentence using the project facts. If the explanation only mentions that interest was paid, revisit the activity evidence.

Change one fact at a time. Suppose Rimal’s complete inactive suspension lasts only April and May, with qualifying work resuming on 1 June and continuing to year-end. Keeping every other assumption unchanged, ten months produce SAR 200,000 of capitalised interest and two months produce SAR 40,000 of expense. The annual cash total remains SAR 240,000. The variation tests the allocation, not a universal two-month threshold; assume this shorter interruption is still extended in its circumstances.

Next, move Nakhil’s readiness date to 31 October while substantial qualifying work continues throughout October. The resulting ten eligible months give SAR 120,000 of capitalisation and November–December expense of SAR 24,000. Explain which date changed and why the engineering conclusion for March and April stayed the same.

Use Accountery’s accounting practice exercises to work on account selection, balanced entries and explaining your treatment. Treat the custom timelines above as your own worksheet practice; this article does not imply that these exact cases are separately available in the exercise library. Pair the practice with your course materials and the official standard references.

A useful review note records three things: the fact you overlooked, the effect on the entry, and the question you will ask next time. That gives your next attempt a concrete improvement to test.